1Repair & Replacement of Damaged Internals at DA Tower 1 on DWG
2E33 Slot 25 Oil Production & Gas Lift Flowlines on DWG
3Replacement of WI Flow Control Valve 3C-FV522591 (Train 2) on DWG
4Replacement of WI Flow Control Valve 3C-FV521591 (Train 1)
5DWG-PCWU Riser R4 Cap Removal for Internal Camera Inspection
6Gas Lift Diverter Valve Installation on DWG
7DWG-PCWU Destruct Part of Ex Valve Support Notch & Construct Valve Support Cover Plates
8DWG-PCWU Replacement of Non-Hazardous Open Drain Pipework
9Replace Cracked Handrail Sockets on DWG
10Installation of Spacer Brackett on DWG 
11Installation of Spacer Brackett on DWG (WN-3DTSZZ-CM-REQ-0154).
12Slot 41 Oil Production & Gas Lift Flowline Installation on DWG 
13DWG DUQ E04 Slot 23 – 5 Off Gas Lift Diverters Valves Installation
14DWG DUQ E04 Slot 23 – Gas Lift Flowline Installation
15CDWG Replacement of Corroded Cable Tray
16DWG (DUQ) E36 Slot26 Water Injection Flowline Installation P&S
17E35 Slot-01 Gas Lift Flowline – Piping & Structural 
18DWG Relocation of Cable Tray Supports
19E38 Slot 07 Oil Production and Gas Lift Flowlines Installation
20Installation of permanent pipe supports in accordance with anomaly at DWG
21DWG PCWU/Replacement of WI flow control valve 3C-FV522591
22E34 Slot 36 Oil Production and Gas Lift Flowlines
23E34 (Slot-36) Choke Valve Replacement
24Installation of New Life Raft & Ampelmann V-Dock Assembly on Chirag-1
25A09 Flowline Modification to Accommodate New X-mas Tree on Chirag-1
26Anomaly Repair of Corroded Main Deck Plating on Chirag-1
27Replacement of Corroded Handrail Panels on Chirag-1 North Helideck 
28A10Z Slot 20 X-mas Tree Change from 6 3/8″ Pneumatic to 5 1/8″ Hydraulic on Chirag-1 
29Drilling Office Handrail Installation on Chirag-1
30Installation of Diagonal Bracer on Chirag-1
31Replacement of corroded steelwork on choke valves access platform
32Chirag 1 CDWG 1146 Part 4  – Installation of Handrails
33CDWG1348 Replacement of corroded supports of instrument devises – Water Injection system
34Re-Routing Existing MEG Lines on Well Bay Area on Shah Deniz
35Replacement of Corroded 2″ BFCC Open Drains Line on Shah Deniz
36Shah Deniz Sewage Treatment Plant Upgrade
37Installation of Additional Supports to Lighting Support Poles on Shah Deniz
38Replace Corroded Pipe Spools 8″ Sea Water Line WS-507074-E01D on Shah Deniz
39Replacement of Corroded HVAC Supports on Shah Deniz
40Installation of Anti-Vibration Supports at Shah Deniz
41Replacement of corroded atmospheric vent line 2-VA-457242
42Replacement of Corroded Steel Water Supply Pipes at Central Azeri to Plastic One

Onshore projects

EA/WA Pipe Supports.

McDermott Caspian Contractors International

January 2004 –   September 2007

HVAC Ductwork.

Kentech

Mart 2004 – July 2005

Call-Off Contract.  

Bos Shelf

January 2004 – May 2006

WREP Repair Work.

BP(GPC)

June 2004 – April 2006

Dada Gorgud Derrick Access Platform.  

Caspian Drilling Company

June 2006 – November 2006

Additional fabrication and installation works  (piping structure and steel structure).  

Bentec

May 2004 – January 2009

Fabrication of Pipe Spools.

Tekfen-Azfen

Mart 2005 –August 2005

Call-Off Works . 

Rolls-Royce

July 2005 – June 2009

Fabrication of Access Platform & Walkways.

Tekfen-Azfen

June 2005 – November 2005

“Istiglal” rig installation works.

BP/CSVC

June 2006 – November 2006

GRE Pipefitter Supply.

Petrofac

September 2003 – January 2005

Additional fabrication and installation works  (piping structure and steel structure).  

Technip

January 2004 – September 2006

Offshore supply of personnel

Maersk

February 2005 – August 2005

FRP fabrication works

Amec-Tekfen-Azfen

October 2005 – November 2007

Supply of Offshore Trades (Shahdeniz).

BP

Mart 2006 – January 2007

Additional fabrication and installation works  (piping structure and steel structure).   

Saipem

May 2004 – June 2007

Fabrication of Pipe Spools.

BP

June 2006 – December 2006

Fabrication and installation works.

Schlumberger

May 2008 – November 2008

Installation works at BTC warehouse.

BTC

Mart 2008 – May 2008

Fabrication and installation works  (piping structure and steel structure).   

KCA Deutag

December 2003 –November 2007

Fabrication of Platforms & Walkway/Bridge.

Encotec

September 2006 –November2006

Supsa Pipeline Repair and Excavation Works. 

AIOC

Mart 2008 –May 2008

Inspection Works at Power Generation & Turbine Plant Installation in Sumgayit

Azenco

Mart 2007 –May 2008

Fabrication of Piperacks, Control Stations, Access Platforms, CS & SS Pipework & Pipe Supports for Shah Deniz HP/LP Flare Upgrade.  

BP

December 2011- December 2014

Asphalt Road Repairs Project at Sangachal Terminal.

BP

June 2012- December 2014

Fabrication & Installation of Pipework for DPCU-1 Compressors at Sangachal Terminal 

AIOC

February 2013 -İun 2014

Fabrication & Painting of Pipe Spools for Gas Lift Compressor Station.

CW Singapore PTE

June 2013 -December 2013

Fabrication & Installation Works for Assembly of Patrol Ships.

İsrael Shipyard Company

June 2014 – November 2014

Fabrication of Piperacks for Shah Deniz 2 Project. 

Tekfen-Azfen

September 2014-June 2016

Fabrication of Non-Steel HDPE Pipes for Shah Deniz 2 Project.

Tekfen-Azfen

October 2014 -April 2016

Fabrication of CS Pipe Spools for Shah Deniz 2 Project.

Tekfen-Azfen

October 2014 – September 2016

Fabricaiton and installation works for modernization of workshop No.9 project

Bos Shelf

December 2014 – October 2015

Construction of off-s[ec Drainage channel at Sangachal Terminal

AIOC

May 2015 -November 2015

Fabrication Services for 16″ NRV Structure, Mudmat & Tie-in Spools.

AIOC

September 2015 -July 2016

Road Repair Works at Sangachal Terminal.

BP Caspian Sea

November 2015 – January 2016

Removal of Sleeve (Casing) Enclosing Pipeline, Blasting & Recoating of Pipeline at WREP KP141.

AIOC

November 2015 – February 2016

Excavation of Pipeline & Shoring of Trenches at PSA-2.

BTC

November 2015 -Mart 2016

Excavation of Pipeline & Shoring of Trenches at PS-05.

AIOC

November 2015 – April 2016

Fabrication of Access Platforms, Walkways & Ladders. 

Bos Shelf

November 2015 -May 2016

Excavation of Pipeline & Shoring of Trenches.

AIOC

May 2016 -August 2016

Fabrication & Installation and NDT services at Khankendi vessel

Baku Shipyard

May 2016 –  April 2016

On-going projects

Metal structure fabrication for OSR equipment

AIOC

April 2017 – on-going

Tank Outage project.

AIOC/BPSD

May 2017-ongoing

Fabrication & Installation of Pipe Spools & Supports for at SD Pig Receiver Area.

BPSD

December 2016-ongoing

Fabrication & Installation of Shoring Structures for 12″ Condensate Line Excavation.

BPSD

February 2017-ongoing

ACG Crude Oil Tank 1 Repair Works.

AIOC

November 2016-ongoing

Replacement of CAMP Hot Water Lines.

BPCS

December 2016-ongoing

Drilling 9 boreholes at ST.

BPSD

May 2017-ongoing

MQS Support for SDT TAR 2017 Activities.

BPSD

August 2017-ongoing

MQS Support on ACG Train-3 Outage Activities

AIOC

April 2017-ongoing

Fabrication of Spools & Supports for SDT TAR 2017.

BPSD

April 2017-ongoing

SD Gas Leak 6″ Pipe Repair. c

BPSD

April 2017-ongoing

SD MEG Line Leak Point Repair on 4″ Pipe.

BPSD

April 2017-ongoing

Construction of Foundations, Fabrication & Installation of Access Platforms.

BPSD

April 2017-ongoing

Provision of Plant & Equipment for SDT 2017 TAR Activities.

BPSD

April 2017-ongoing

Fabrication, material supply, painting, assembly and delivery to site of truss in tobacco processing – receiving facility located in Gakh region.

Inter Tobacco

May 2017-ongoing

Floor Levels La Luna Hotel Steel Work Errection and Subsructure Assembly for 2nd and 3rd Liffting.GILAN HOLDING LLC2019
DWG – Deep Water Gunashli – Offshore Projects
Shah Deniz – Offshore Projects
Chiraq 1 – Offshore Projects
BP2019
Gusar 5000 ton Refrigerator ComplexAcrarko LLC2019
Metal construction works of Zagatala Hazelnut Processing PlantAqrarko LLC2021

      Georgia

 Completed projects

Welder  Qualification Test for SCPX.

BP

May 2015-February 2016

Tie-in 101 Split tee welding SD2. 

BP

Mart 2016- April 2016

In Service Welding for Hot Taps

BP

Mart 2017- April 2017

Supsa Cost B foam Ring Pipe Replacement.

BP

November 2016-April 2017

The welding repair of the foam system pipe supports of Supsa tank B.

BP

January 2017-Mart 2017

MVS Valve testing.

BP

February 2017-April 2017

PSG1 Grid Power Project Mechanic & Piping support.

BP

June 2016-February 2017

PSG2 MOL 4 Change Out.

BP

September 2016-February 2017

Removal of insulation and blasting of 42” pipes.

BP

February 2017 – Mart 2017

IF Kit Replacement support at EDDF.

BP

August 2016-August 2016

Tank VC Injection Support.

BP

September 2016-October 2016

Installation of EMS Fire Escape Stairs at PSG1.

BP

January 2016-October 2016

On-going projects

Supsa Cost D foam Ring Pipe Replacement

BP

October 2016-ongoing

Supsa Cost A foam Ring Pipe Replacement

BP

January 2017-ongoing

N2 Bottle Coating Repair

BP

July 2016-ongoing

Supsa PLR Installation

BP

May 2017-ongoing

Lilo Warehouse Support Services Phase II

BP

September 2014-ongoing

Water treatment Package  Support at PSG2

BP

June 2015-ongoing

PSG 1 entrance door welding works

BP

May 2017-ongoing

Piping fabrication services

Saipem

July 2016-ongoing

Supsa PIG Trap Trial fit up and Testing

BP

April 2017-ongoing

PS 13 Tank outlet fitting fabrication

BP

Mart 2017-ongoing

      Iraq

X-ray and welding of the 40” Iraqi-Turkey pipeline crossings at the Riyadh and Zegeton canals 

TRIQUEST INTERNATIONAL GROUP LTD

June 2006 – July 2006

Turkey

Lifting 32” pipe structure with air cushion    

BTC

November 2013–November 2013

Welding of 7 off pipe support shoes at Pump Station.

BTC

November 2013–November 2013

Kazakhstan

Construction of Karabatan Refinery Factory 

GATE INSHAAT

2007 – 2011

Pipe Rack Fabrication.

ERSAI / Kashagan

2007-  2011

Kashagan Offshore Hook-up and Commissioning of Complex D and Island A Offshore Facilities.

Aker Kvaerner Contracting AS.

2007- 2011

Hook-Up, Pre-Commissioning and Commissioning Assistance Project.

CCEP

2007- 2011